Recently the first delivery with 15 electrolysers arrived in Utah, the HydrogenPro stated.The facility will combine a 220-megawatt bank of high-pressure alkaline electrolysers from HydrogenPro and a storage capacity of 4.5 million barrel salt caverns to store clean hydrogen.
The contract includes a total of 40 electrolysers and 20 gas-separation skids. HydrogenPro will complete manufacturing of the electrolyser systems in 2023, followed by instalment and commissioning on-site completed in late 2024.
Press release https://is.gd/WAQJVH